Costs and Funding Sources


SOURCES of FUNDS

Expected Sources

Money Provided by School

$1500

Sale of Green Tags

$2000

Kansas Energy Office Support

$1000

Money or Services Donated

Cost of materials and installation


PROJECT PARTS LIST (Local utility and/or local business contribution)

Listed below are some additional items that will need to be purchased in order to completely install a SkyStream 3.7 turbine.  All the wire and conduit prices will vary depending on how far it is from your turbine to the school connection.  These items will hopefully be donated by local businesses or utilities.  Note:  You will not need ALL of the items listed below.  Items will be dependent upon the choice of a 240V or 120V connection.

Additional Items for Turbine and Tower

Qty.

Material

Cost

2

Copper Grounding Rods (3/4�)

$30 each

1

Tower base fused disconnect box

$118

1

School disconnect box

$118

3

AWG 10 turbine electrical wire (80ft)

 

300ft

120V Turbine Wire
(Nacelle to tower disconnect)

$214.50

300ft

240V Turbine Wire
(Nacelle to tower disconnect)

$296.70

Varies

Steel Electrical conduit

$11.20 per 10ft length

Varies

PVC Schedule 40 Electrical conduit

$6.53 per 10ft length

Varies

Steel exterior grade electrical conduit

Varies

Varies

Turbine interconnection electrical wire (from tower disconnect to school) *

Varies

*See Wiring Prices table below.

Below is a table listing approximate wire prices.  The prices will vary depending on how far it is from the turbine to the school.  The price also changes when using 240V versus 120V.  The price does reflect the use of a contractor and a 30% markup. 

Wire Prices (installed)

Voltage

Lengths

Total Cost

120V

50ft to 500ft

$14 - $1000

240V

50ft to 1000ft

$20 - $3000


TURBINE COSTS (School plus green tag contribution)

The cost of the SkyStream 3.7 is described below. Included is the retail price of the turbine as well as the cost NREL has been given from the SkyStream manufacturers.

Turbine Cost Estimates

Retail Cost**

$6000.00

Non-profit, Schools Discounted Cost

$3250.00

 

 

** This is an estimated price. The actual price will vary from dealer to dealer.

TOWER AND FOUNDATION COSTS (School and/or community support contribution)

There are a couple of options regarding the style of tower for use with the SkyStream 3.7 turbine. Below is the estimated cost of each type of tower and foundation.  All the prices for materials are subject to change due to the market.  This is just an estimate for your use.

70-ft Guyed Tower & Foundation Cost Estimates (all costs are rounded)

Qty.

Material

Cost

Tower

 

 

1

Tower Kit (Skystream)

$894.00

1

Tower Adaptor (Skystream)

$84.00

1

Lightning Protection Kit (Skystream)

$50.00

2

3/4"x 12" Eyebolt

$5.00

2

3/4"x 8" Eyebolt

$5.00

 

5" Sch40 Steel Pipe

$956.00

Total Tower Cost

 

$2000.00

 

 

 

Foundation

 

 

 

Concrete**

$550.00

177.5 ft

Rebar #3

$0.18/ft

137.5 ft

Rebar #4

$0.28/ft

20 ft

Rebar #6

$0.63/ft

 

 

 

Total Foundation Cost

 

$633.00

 

 

 

Grand Total for Guyed Tower

 

$2650.00

 

60-ft Monopole & Foundation Cost Estimates (all costs are rounded)

Qty.

Material

Cost

Tower

 

 

1

60-ft Monopole Tower

6350.00

1

Lightning Protection Kit

$50.00

Total Monopole Cost

 

$6400.00

 

 

 

Foundation

 

 

 

Concrete**

$500.00

335 ft

Rebar #4

$0.28/ft

225 ft

Rebar #8

$1.05/ft

 

 

 

Total Foundation Cost

 

$830.00

 

 

 

Grand Total for Monopole

 

$7250.00


ADDITIONAL EQUIPMENT COSTS (Local utility and/or local business contribution)

There may be some additional costs to install the turbine initially. This includes rental of trenching and digging equipment and also the use of a licensed electrician. As with other prices this is just an estimate.

Additional Equipment Costs

Trencher

$150/day

Electrician

$30/hour